Liberals’ 2-year infrastructure plan set to take 5: documents

Government says 793 projects totalling $1.8 billion in federal funds have been granted extensions

Late last year, officials warned that a federal spending spree to repair crumbling roads and water systems could take three years longer than expected to complete, based on internal documents outlining issues with the first tranche of cash in the federal government’s infrastructure program.

The federal government had originally hoped to have cities and provinces complete $5.4 billion in transit and water system work by this March, but quickly realized that more time was needed.

A “secret” fall briefing note to Infrastructure Minister Amarjeet Sohi, obtained by The Canadian Press through the Access to Information Act, says delays hampered a large number of construction projects, requiring that the deadline be extended as far as March 2021.

The heavily blacked-out document predicted the majority of water and transit projects “would require extensions not only for a third year, but beyond into a fourth year (i.e. 2019-20) and fifth year (i.e. 2020-21),” referencing the federal fiscal years in brackets.

Sohi agreed to a blanket deadline extension to March 2020, turning what was to be a two-year stimulus program into a four-year plan.

He said the decision to grant extra time to 2020, instead of 2021, was based on the expected cash flow for projects and the ability for construction companies to handle all the extra work.

“This is not about that projects are being delayed, it’s about taking a little longer to complete those projects or taking a little longer to have the buses manufactured because of construction and manufacturing capacity,” Sohi said in an interview from Edmonton.

“From our perspective, we made a commitment to build and rebuild infrastructure and focus on the repairs in phase 1 and … we are achieving the results we intended to achieve, but we also want to give flexibility.”

As of Friday, the federal government had approved more than 3,400 water and transit projects with a combined federal contribution valued at almost $4.2 billion. Of that money, federal coffers had only doled out about $175.6 million to date, based on figures available on the Infrastructure Canada website.

Federal dollars flow once cities and provinces submit receipts for reimbursement, often creating a lag between when work takes place and when the federal money is spent.

In some cases, the federal government won’t receive receipts until a project is completely done. In other cases, projects are delayed because of labour strife, bad weather or other factors beyond Ottawa’s control.

The government says 793 projects representing about $1.8 billion in federal contributions have been granted individual extensions from Sohi. Between those extensions, and delays in filing expense claims, federal officials last year decided to shift more than $2 billion in planned spending to future years.

Provincial and municipal officials say that the time needed to go through the funding approval process contributed to the delays.

Having officials vet the details of each proposal before getting federal approval for funding meant some cities put off breaking ground until they knew federal funding would come their way.

“We heard loud and clear from some municipalities that they were struggling to meet two pieces of criteria: timeline requirements and a provision that would require municipalities to incur 60 per cent of their costs by March 31st, 2018,” said Alex Benac, a spokesman for Ontario Infrastructure Minister Bob Chiarelli.

The extra time and removal of the local spending requirement, which Chiarelli asked for in September, has given cities “much-needed time to get shovels in the ground and keep their projects on track according to a more generous, achievable timeline,” Benac said.

Federal and provincial officials say the lessons learned from the first phase of the program will be used in designing the second phase.

Both sides want funding agreements for the second, longer and more lucrative phase of infrastructure spending signed by March.

Jordan Press, The Canadian Press

Like us on Facebook and follow us on Twitter.

Just Posted

School trustee candidates debate

Candidates for School District 6 (SD6) Trustee gathered at McKim on Tuesday… Continue reading

VIDEO: This is what buying legal pot in B.C. looks like

Take a look inside B.C.’s first and only legal pot shop located in Kamloops

Kimberley’s cannabis stores are open for business

Both are working through the process for a legal permit

Fatality on Hwy 93/95 near Radium

Accident by Juniper Heights shuts down highway

Know it All entertainment listings

Event cancelled The Kimberley Rotary Club regrets to announce that our Bones,… Continue reading

Kimberley Mayoral forum at McKim

A summary of the topics discussed at Tuesday night’s Mayoral candidate forum.

Police hand out a few hefty fines for allegedly violating Cannabis Act

Police in Canada posted a photo of a $215 ticket given to someone who allegedly had a baggy of marijuana in their car

Great British Columbia ShakeOut earthquake drill reminder

Don’t miss the opportunity to participate in the Great ShakeOut

Jagmeet Singh says marijuana pardons are not enough

Trudeau government will streamline pardon process for Canadians convicted of simple possession of marijuana in the past

BC Ferries begins taking debit in two-month pilot project

Company is giving customers option to use Interac on two-month trial on select vessels

Caregivers banned from smoking, growing cannabis around children-in-care: MCFD

Ministry has limited cannabis use for caregivers, stating it may “pose a risk to children and youth.”

Cheaper strains sell out within minutes on online BC Cannabis Store

Province says new strains will become available in the coming months

Only 40% of B.C. car dealerships have electric cars available: report

Researchers found buyers frustrated at the lack of options

Most Read